Suppose two suppliers quote for qualification of a new packaging line. Both include installation qualification (IQ) and operational qualification (OQ). One price covers writing the protocols. The other includes field execution, review of the vision-system vendor’s test results, one retest visit and a final report. Procurement cannot resolve that difference by comparing day rates.
Draw the boundary at the interfaces
A line may arrive under one purchase order while the labeler, vision system and reject mechanism come from different suppliers. Ask who will demonstrate that a carton with an unreadable code is rejected by the installed line and that the system records the event. A camera supplier may have tested detection at its factory. The integrator may have tested the reject device separately. Both can complete their contracts while the end-to-end test still has no owner.
Put that integrated check on its own line in the scope. Name who writes the test, supplies the challenge materials, makes the line available, executes the test and investigates a failure. Assign review and approval according to the owner’s quality procedures.
Describe what the price includes
For each system, separate document preparation, execution and closeout. State the expected number of review cycles and site shifts. Specify who provides vendor support, operators and access to controlled records. Ask each bidder to identify exclusions and to price extra attendance or retesting on the same basis. An unpriced dependency becomes a schedule problem as soon as the vendor leaves site.
A scope line you can issue for pricing
Illustrative packaging-line work package. Prepare an OQ protocol for the integrated vision and reject function. Include one owner review cycle, one on-site execution shift and an indexed report of results. Owner supplies approved challenge samples, an operator and access to the line. Integrator attends execution and owns software corrections. Bidder to state the rate and lead time for a return visit following a correction. Site Quality retains approval under the site procedure.
Before award, give both bidders the same open-items list and have them return a revised price against it. You should be able to point to a named party and a priced activity for every test on the critical path.
Technical reference. The division of contractual work above is illustrative. The ISPE Baseline Guide, Volume 5, Commissioning and Qualification provides the risk-based framework for determining what needs to be verified.
Zyme can review the system list and proposed division of work before you issue the package. CQV planning and execution.



