Which factory tests should you repeat on site?

A factory test can prove what a machine did at the supplier’s premises. Whether it supports qualification depends on the requirement, the record and what changed on the way to site.
Vials passing through a pharmaceutical filling machine

A vendor demonstrates an alarm by forcing an input at the control panel. The display shows the right message and the factory acceptance test (FAT) passes. At site, the question is whether a signal from the installed instrument reaches the controller and produces the required response. The factory record answers one part of that question. Repeating the same input simulation on site would still leave the field connection untested.

Make the decision against a requirement

Before the FAT, review the vendor protocol alongside the approved user requirements and the equipment design. For each result you intend to use, record the requirement it supports, the configuration under test, the expected result and the record the owner will receive. Agree the approach under the project qualification strategy. A pass mark on a vendor summary is of limited use if the underlying record cannot be traced to the machine being installed.

Three different decisions on the same machine

Retain the evidence. A material certificate is traceable to a uniquely identified component inspected at the factory. If the component can still be identified at receipt and the change record shows it was retained, the certificate and inspection record can support the material requirement. The site still verifies that the correct component is installed.

Retain part and test the interface. The alarm simulation established that a particular software revision displayed the specified message. Keep that result if justified. Test the path from the installed instrument through the field wiring and controller to the required response. Record where the factory test ended and the site test began.

Reassess after change. If the vendor changes the alarm logic after the FAT, identify the affected requirement and tests against the new revision. A signed factory protocol remains a record of the earlier configuration. It cannot, by itself, establish how the revised logic behaves.

Close the decision at receipt

At shipment, obtain the executed protocol, supporting records, open exceptions and hardware and software identifiers. At site, compare those identifiers with the installed configuration. Give each test a recorded disposition, its rationale and an owner for outstanding work. That record explains both why a test was repeated and why another result was accepted.

Technical references. For projects applying EU GMP, Annex 15, sections 3.4–3.7 addresses use of factory tests and the impact of transport and installation. For U.S. projects, FDA’s Process Validation guidance, section IV.C.1 discusses qualification of equipment and utilities.

Preparing for a factory test?

Zyme can review a vendor protocol and identify which results the site can use and which checks need to run after installation. Equipment and utility qualification.

Project enquiries
Related articles

22 Nov 2026

22
Nov
Project team reviewing a diagram on a glass board
Insights

Writing a CQV scope that contractors can price

Two bids can cover the same equipment list and buy very different amounts of work. A packaging line shows where the difference enters the price.
Read Article

22 Nov 2026

22
Nov
Vials passing through a pharmaceutical filling machine
Insights

Which factory tests should you repeat on site?

A factory test can prove what a machine did at the supplier’s premises. Whether it supports qualification depends on the requirement, the record and what changed on the way to site.
Read Article

Let’s discuss
your next project

Tell us which systems are in scope and the date of your next design review, factory test or handover. We can use those details to scope the work with your team.
Discuss your project
Explore our services